5.7.8: Component pool process

<< Click to Display Table of Contents >>

Navigation:  Main modules > Log / Purchase >

5.7.8: Component pool process


How to deal with an equipment pool?

1

When provisioning is requested (PR) for a component which is to be procured under a pool agreement, the global process will be as follows:

a/ REQ (Requisition)

clip0454

b/ M.REC (Material delivery and reception)

clip0455

c/ REST (Restitution of the core unit)

clip0456

d/ M.OUT (Shipment of the core unit)

clip0457

 

Click on the above buttons to go to the associated section of this manual